Where regulator is going, in three milestones, and what each closes. The build's open debt is one row each in docs/DEBT.md; this page maps those rows to milestones and issues so a contributor can pick one up, and lists what is not planned so nobody re-files it. The registry cards stay the source of truth for what a regulator does not catch; an item here that pays a row says which.
Milestones are labels on issues (roadmap:0.1, roadmap:0.2, roadmap:0.3). Dates are not promised; order is.
0.1 — Operable
The reference build is a published product a team can install into a repository, run under CI, and read the documentation for. Done. The six packages are on npm (#44; 0.1.3 is current, each patch a live run's finding — the changelog says which) and the documentation site is on GitHub Pages (#45).
Done in 0.1: the regulator CLI with init and doctor; the S3 loop over two workloads; forty-two active regulators with REGULATORS.md and BOUNDARY.md rendered from the registry; host-run evidence at closeout; obligations, delivery and the algedonic path; the eval harness with four committed scripted reports; the Pi host as its own package behind the host seam; the docs site; the course in its own repository.
0.2 — Trustworthy
Evidence about the regulators under a live model, and the checks the cards already name as their next step. This is the milestone that turns the registry's claims into measured ones and closes the debt that a card's own retirement condition points at.
| Item | Pays | Issue |
|---|---|---|
| A live eval report over the drift scenario, with an interpretation; the model router's failover observed end to end | rows 33, 15 | #46 |
| Planner-quality graders over the result reports' diagnostics | row 40 | #49 |
inherited-tests: per-assertion diff, a test-layout convention, a cached base run | row 41 | #50 |
Definition versions: a migration note per release and regulator upgrade for instances | row 39 | #53 |
Behaviour checks beyond Function.length: a probe a contract can carry | row 35 | #54 |
| Fixture: the flaky test and the migration that must not be re-run | row 13 | #55 |
The viability case rendered from the registry (VIABILITY.md), the capstone's artifact | — | #57 |
0.2 is done when the live report is committed, every row above is struck or moved to "not planned" with a reason, and regulator review --due is clean at the first review date (2026-12-01).
0.3 — Community
The seams proven by a second implementation on each side of them: a second host, a third workload, and the mechanisms that make an instance event-driven rather than polled.
| Item | Pays | Issue |
|---|---|---|
A second host behind the host seam, with BOUNDARY.md saying which hosts enforce which gate | — | #58 |
| Route on append: watch the regulatory log and the ledger; delivery as a hook, not a poll | row 23; outbox-watcher retirement | #59 |
| Per-tool consent grants as a profile field, enforced by interception | row 29 | #60 |
| A third workload, contributed: the authoring guide and a template | — | #61 |
| Semantic S2: typed coordination commitments between units | — | #14 |
Alongside: a contributor pathway (CONTRIBUTING.md, issue templates for a bug, a debt row and a proposal), and the course's first cohort pinned to a release tag.
Threads — designed, not yet scheduled
Work that has a design note but no issue yet. Each row points at the note that holds the design and names the one next step, so a thread can be picked up without rereading the conversation that started it. A row leaves this table when its first slice becomes an issue in a milestone above and nothing designed is left behind it, or when it is dropped (the note's status says why). A thread with later slices keeps its row and names the issue its current slice is in.
| Thread | Design | State | Next step | Fits |
|---|---|---|---|---|
The system's figures generated from the definition: the loop, the session's gates, the workload, the recovery lattice, the unit lifecycle, who writes where — as views in the control room beside the six-column topology, in the docs by regulator docs --write, copied by the website | open questions §1 | decided; first slice landed | The typed enforcement points landed (#76: ENFORCEMENT_POINTS in protocol, five places with closed lists held against the code). Next: the generator over them and regulator docs --write for the SVGs | 0.2 |
| A person can raise S4 intelligence; sensors declared in the definition | open questions §2 | proposed | regulator intelligence report --by … writing the same intelligence-signal under human:<name> provenance | 0.3, beside #59 |
| Units that run a program, not a session | open questions §3 | answered: the dispatcher seam already allows it | A command runner per unit type in the workload definition | 0.3, beside #58 |
| The first live drift runs: what each found, and what the live report must say | live drift runs note §3 | three defects found and fixed (0.1.2, 0.1.3); the numbers so far are interim | Rerun on 0.1.3 with the interpretation written; commit the report and close #46 | 0.2 |
| Predictive S4: predictions as intelligence signals that resolve and are graded on calibration | open questions §4 | exploratory | Waits on the live eval report (#46); then an instrument record kind in the registry | after 0.2 |
| ArticleMiner as a knowledge-production workload | ArticleMiner note §5 | proposed, in phases | Phase 1: declared checks for non-Node domains (§4.1) | 0.3, under #61 |
| A homelab control plane, designed with its infrastructure | homelab note §7 | design note; ten of thirteen decisions made (§9) | Choose the file service (§9, decision 11); then stage 0 in a separate homelab repository | unscheduled |
| The control room accepts the CLI's dispositions | open questions §5 | deferred: the control room stays read-only for now | None until reopened | — |
The open questions' backlog (§6) holds smaller items with no design yet; one becomes a row here when it gets one.
Not planned
Rows that are the deployment's, or that go with work this project has deferred. Listed so they are not re-filed as debt; each stays on its card as a limitation and in BOUNDARY.md as a route not covered.
| Row | Why not here |
|---|---|
| 4 — evidence carries the orchestrator's host, not the target platform | The environment matrix is CI's; the closeout records where it ran. |
8 — bash is outside most mechanisms | Real isolation is the operating system's or a container's; the shell's reach is declared in the deployment (OPERATING.md, security posture). |
| 9 — leases and the effect journal are files on one machine | Cross-host coordination goes with full VSM recursion, which is deferred. |
| 14 — the thrash detector's count restarts per session | S2 state across sessions goes with recursion. |
| 19 — nothing watches network egress | Containment is the operator's; the canary watch sees tool results and text. |
| 26 — nothing checks a remembered fact is true | A truth check is a person's review; the expiry is the pressure. |
28 — --by is asserted, not authenticated | Authentication belongs to the deployment; the disposition-authority card retires when a signed disposition replaces the name. |
| 38 — the outbox watcher is a process, not a service | Supervision and the channel are the deployment's; #59 changes what it watches, not who restarts it. |
Deliberately deferred, as in AGENTS.md: RDF/SHACL, full VSM recursion, broad S4 integrations, autonomous S5 mutation, production-grade benchmarks. GSD-Pi is comparison material in the course, not a dependency.
How this page is kept
This section is how work is tracked in this repository, for people and for agents; AGENTS.md and CONTRIBUTING.md point here rather than restate it.
Work moves through four places, one per stage, and each thing is written in one of them:
| Stage | Where | What it holds |
|---|---|---|
| An idea or a question | docs/research/2026-09-25-open-questions.md (running), or a note of its own under docs/research/ when it has one source | the design, and why |
| A gap a card already names | a row in docs/DEBT.md | what is owed, and which card says so |
| Designed, with a next step | a row in the threads table above | the order and the one next step |
| Scheduled | a GitHub issue with a roadmap:0.x label, and a row in that milestone's table | the acceptance criteria and the rows it pays |
- A design that comes up in conversation is written into a note before it is acted on; a decision taken in conversation is recorded in the note it decides (a "Decided (date)" paragraph), not only in the chat.
- A note that names a next step gets a threads row in the same change. When that step becomes an issue, the issue joins a milestone table and the threads row names it; the row leaves when nothing designed is left behind it.
- An issue is written as What (the gap, citing the file), Why (the note or row it comes from), Debt paid when it pays rows, and Done when (checks a reviewer can run), and ends with its roadmap line. Labels:
roadmap:0.x, plusbug,good first issueorproposalwhere they apply. - Before an issue is filed from a work list, the list is re-checked against
main: lists go stale, and an item already fixed is struck in the note, not filed. - The change that lands an issue removes its row from the milestone table, strikes what it pays in
DEBT.mdand the note, and updates the card, in the same pull request. - A milestone closes with a changelog entry and a tag; the next milestone's list is reviewed at that point, not before.